08/01/2014 - 13:19

As we enter into our last month of the project, the new brick paver streetscape, stamped concrete areas, and other decorative fixtures are beginning to be installed.  Construction in the upcoming week will include work paving St. Johns Avenue, sections of Chapel Hill Road, and the completion of major concrete items.

Read more


07/25/2014 - 11:07

Work will continue next week on the reconstruction of St. Johns Avenue with new curb, sidewalk, and driveways within the project limits.  We will also be working to install and wire the new decorative and intersection lighting near the roundabout.

Read more


07/18/2014 - 11:30

The intersection of Johnsburg Road and Chapel Hill Road is now closed to all traffic.  Construction will progress next week with work on a concrete retaining wall, lighting, and the completion of the storm sewer system along St. Johns Avenue.

Read more


07/11/2014 - 09:36

Monday, July 14, 2014, asphalt paving will begin on the north side of Johnsburg Road include portions of the roundabout.  Please be prepared for an increase in construction traffic throughout the construction zone.  

Read more


07/03/2014 - 09:05

Weather permitting on Thursday July 17th, the intersection of Johnsburg Road and Chapel Hill Road will be completely closed to traffic as the final stages of the Johnsburg Road Roundabout project are completed.  The intersection is expected to be reopened during the first week of September.  Motorists should follow posted routes to detour around the closed intersection.

Read more